Barby Road closes from Monday 16 November as work starts on traffic lights at its junction with Ashlawn Road and Onley Lane. The scheme runs to summer 2027.

Barby Road will close from Monday 16 November as work starts to put traffic lights on its junction with the B4429 Ashlawn Road and Onley Lane. Warwickshire County Council says the scheme will take until summer 2027.

The council announced the start date in a news release today. Its scheme page gives the same date.

What is closing, and when

  • From 16 November: Barby Road is closed on its north-west arm, for up to 300 metres from the junction.
  • Early 2027: once Barby Road reopens, Onley Lane closes on its south-east arm, for up to 200 metres from the junction.
  • Now and then: a small number of extra one- or two-day closures may be needed for particular parts of the job.

Temporary traffic lights will run at the junction for much of the work. They will be manned on weekdays at peak times, from 7.30am to 9.30am and from 3.30pm to 6pm.

The council has not published a diversion route for the Barby Road closure. It says it will give dates for the shorter closures as the work goes on.

What is being built

The work will put the whole junction under traffic signals. The list in the council’s release includes:

  • traffic signals at the Ashlawn Road, Barby Road and Onley Lane junction
  • Toucan crossings, for people walking and cycling, on the Ashlawn Road and Barby Road arms
  • a wider Ashlawn Road, with two lanes on the eastbound approach
  • resurfacing, wider footways and better drainage
  • new signs, road markings, kerbs and street lighting

The county’s Section 278 programme for Rugby adds that the existing cycleway will be improved. National Cycle Route 41 needs a small realignment.

Why it is happening

The junction is being rebuilt to meet planning conditions on a nearby David Wilson Homes development. Rugby Borough Council and the county set those conditions to deal with the extra traffic the new homes will bring. The developer pays for this kind of work under a Section 278 agreement with the county, and Montel Civil Engineering is the contractor.

Councillor Stephen Shaw, the county’s portfolio holder for transport and planning, said the scheme was “a significant investment in Dunchurch’s transport infrastructure”. He added: “While we recognise there will be some temporary disruption during construction, these improvements will deliver long-term benefits for residents, businesses, pedestrians, cyclists and motorists alike.”

What it means for you

  • Using Barby Road to reach Ashlawn Road or Dunchurch? Plan another route from 16 November. No signed diversion has been published yet, so check one.network before you set off.
  • Driving Ashlawn Road at peak times? Expect temporary lights at the junction for months. They will be manually controlled in the morning and afternoon peaks.
  • Walking or cycling? The finished junction will have controlled crossings on two arms, and the cycleway will be improved.
  • Questions go to the county’s Section 278 team at s278teamenquiries@warwickshire.gov.uk, or call 01926 412515.

Everything else closing around the town this week is on our Rugby roadworks page.